Completed -
The scheduled maintenance has been completed.
Jul 18, 17:45 CDT
In progress -
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Jul 14, 07:45 CDT
Scheduled -
Critical Impact: During this maintenance, customers will experience a loss of redundancy. If your systems are connected to the specific UPS system undergoing maintenance and are not dual-powered, they will lose power during that period.
Maintenance Window
Start Date/Time (Local): July 14, 2025, at 7:50 AM
END Date/Time (Local): July 18, 2025, at 5:00 PM
Detailed Maintenance Schedule
Tuesday, July 15, 2025 Electrical teams will perform maintenance on the following UPS systems:
9:00 AM: Power down UDPAA110 and UDPAB110
9:10 AM: Power down UPSAA110, AB110, and AC110
9:20 AM: Power down MSBA0110
2:00 PM: Restore power to MSBA0110
2:30 PM: Restore power to UPSAA110, AB110, and AC110
3:00 PM: Restore power to UDPAA110 and UDPAB110
3:30 PM: Transfer all PDUs to UPS power
Wednesday, July 16, 2025 Electrical teams will perform maintenance on the following UPS systems:
8:00 AM: Power down PDUs and RPPs fed from UDPB0110
8:10 AM: Power down UPSBA110
9:20 AM: Restore power to UPSBA110
9:40 AM: Restore power to PDUs and RPPs fed from UDPB0110
Friday, July 18, 2025
8:00 AM: Power down F system
2:30 PM: Restore F system to normal power
3:00 PM: Check all systems for normal operations and clear alarms.
Testing Completion: 5-Year Breaker Testing will be completed after the final checks on July 18, 2025.
Action Required: Please review this schedule carefully and take necessary precautions if your equipment is single-powered or dependent on redundancy during these specific times.